CUMBERLAND – Permanent replacement of the Rawson Pond Dam is set to commence shortly, funded through $1.7 million in borrowing from a fledgling state program.
On Nov. 4, the Cumberland Town Council approved a resolution authorizing borrowing up to $1.7 million through the Resilient Rhody Infrastructure Fund program. The new program from the Rhode Island Infrastructure Bank is designed to support projects that increase a municipality’s resilience to climate change while preserving local ecosystems.
The new dam is expected to be completed by next spring.
Fourteen months ago, the council, by a 5-1 vote, approved a permanent dam replacement, ending months of debate over whether the town should invest in an old dam that isn’t considered critical infrastructure. The pond it created, however, is considered a local ecosystem, and neighbors who live on it also emphasized diminished quality of life and property values after the dam gave way in January 2024 and the pond largely emptied.
The council approved a sheet pile dam with a 50-year lifespan, which was presented as still being less expensive than a 100-year cast-in-place spillway.
DPW Director Romeo Mendes told the council that the total cost for reconstruction is more than $1.6 million, according to a bid and contingency, and it was rounded up to $1.7 million.
There are a couple of different options for paying down the loan, and they’ll do whatever the town’s bond counsel recommends, said Mendes and Mayor Jeff Mutter. That move will also be brought back to the council for approval, they said. This resolution, said Mendes, keeps the process moving.
Councilor Lisa Beaulieu asked what the borrowing will end up costing the town over 20 years, and Mendes said that hasn’t been calculated yet. He said interest rates were at one time in the 4 percent range, and the way loans through the Infrastructure Bank work is that they give 25 percent off the best rates. Based on current rates, he said, they’ll probably pay in the range of 5.5 percent interest.
The dam was first constructed between 1822 and 1838, and despite its deteriorated condition, the town took possession of it a decade ago. It was used to support ice harvesting from the 1880s through the 1930s, and likely a grist mill and sawmill before that.
Mayor Jeff Mutter has said there should have been a maintenance plan in place for the dam, and it is not believed that there ever was one. When the town took possession of the pond and dam in 2017, it came at the same time it was under a consent agreement to replace the water treatment plant at Speech Pond. Wells have since come online at nearby Franklin Farm.
Mutter has said the previous administration could have conducted more due diligence before purchasing the dam, suggesting that there may have been reasons for the purchase beyond protecting a water source.
Though the original statements about the purchase weren’t entirely accurate, the mayor has said, he doesn’t believe they were intentionally misleading. Officials at the time believed there was some risk of new residential development, and they decided the risk of taking ownership of the old dam was worth it.
Rejecting the project last year would have meant taking down the temporary dam and leaving the larger pond empty.